| Kode RUP |
66704976 |
| Nama Paket |
Rehabilitasi Jalan Paket 03 |
| Nama KLPD |
Kab. Bone |
| Satuan Kerja |
Dinas Bina Marga, Cipta Karya dan Tata Ruang |
| Tahun Anggaran |
2026 |
| Paket Terkonsolidasi |
| No. |
Kode RUP |
Nama Paket |
| 1. |
: [63714609] |
: [Ruas Balangnge - Masago] |
| 2. |
: [66534642] |
: [Ruas Galung - Kajuara] |
| 3. |
: [66535689] |
: [Ruas Galung - Kajuara] |
| 4. |
: [66540707] |
: [Ruas Palattae - Pammusureng] |
| 5. |
: [63714600] |
: [Ruas Padaelo - Lappabosse - Kalero] |
| 6. |
: [63714607] |
: [Ruas Palattae - Pammusureng] |
| 7. |
: [63714610] |
: [Ruas Galung - Kajuara] |
| 8. |
: [63714616] |
: [Ruas Galung - Kajuara] |
| 9. |
: [63714615] |
: [Ruas Balangnge - Masago] |
|
| Lokasi Pekerjaan |
| No. |
Provinsi |
Kabupaten/Kota |
Detail Lokasi |
| 1. |
Sulawesi Selatan |
Bone (Kab.) |
Kabupaten Bone |
| 2. |
Sulawesi Selatan |
Bone (Kab.) |
Kabupaten Bone |
| 3. |
Sulawesi Selatan |
Bone (Kab.) |
Kabupaten Bone |
| 4. |
Sulawesi Selatan |
Bone (Kab.) |
Kabupaten Bone |
| 5. |
Sulawesi Selatan |
Bone (Kab.) |
Kabupaten Bone |
| 6. |
Sulawesi Selatan |
Bone (Kab.) |
Kabupaten Bone |
| 7. |
Sulawesi Selatan |
Bone (Kab.) |
Kabupaten Bone |
| 8. |
Sulawesi Selatan |
Bone (Kab.) |
Kabupaten Bone |
| 9. |
Sulawesi Selatan |
Bone (Kab.) |
Kabupaten Bone |
|
| Volume Pekerjaan |
1 Paket |
| Uraian Pekerjaan |
1 M2 Pembuatan Jalan Aspal Baru Lokal Tipe A; |
| Spesifikasi Pekerjaan |
Setara Lapisan Penyusun Ac-bc tbl. 4 Cm + Ac-wc tbl. 4 Cm + Aggregat A Tbl. 30 Cm + Aggregat B Tbl. 40 Cm + Aggregat C Tbl. 40 Cm;
|
| Produk Dalam Negeri |
Ya |
| Usaha Kecil/Koperasi |
Ya |
| Perkiraan Persentase Nilai Usaha Kecil |
1 % |
| Pengadaan Berkelanjutan atau Sustainable Public Procurement (SPP) |
| Aspek Ekonomi |
Tidak |
| Aspek Sosial |
Tidak |
| Aspek Lingkungan |
Tidak |
|
| Pra DIPA / DPA |
Tidak |
| Sumber Dana |
| No. |
Sumber Dana |
T.A. |
KLPD |
MAK |
Pagu |
| 1. |
APBD |
2026 |
Kab. Bone |
1.03.10.2.01.0055.5.2.04.01.001.00003.1.3.04.01.01.0003.00001 |
3972726660 |
| 2. |
APBD |
2026 |
Kab. Bone |
1.03.10.2.01.0055.5.2.04.01.001.00003.1.3.04.01.01.0003.00001 |
2741575042 |
| 3. |
APBD |
2026 |
Kab. Bone |
1.03.10.2.01.0055.5.2.04.01.001.00003.1.3.04.01.01.0003.00001 |
4049331598 |
| 4. |
APBD |
2026 |
Kab. Bone |
1.03.10.2.01.0055.5.2.04.01.001.00003.1.3.04.01.01.0003.00001 |
1072009004 |
| 5. |
APBD |
2026 |
Kab. Bone |
1.03.10.2.01.0055.5.2.04.01.001.00003.1.3.04.01.01.0003.00001 |
3923395062 |
| 6. |
APBD |
2026 |
Kab. Bone |
1.03.10.2.01.0055.5.2.04.01.001.00003.1.3.04.01.01.0003.00001 |
700002676 |
| 7. |
APBD |
2026 |
Kab. Bone |
1.03.10.2.01.0055.5.2.04.01.001.00003.1.3.04.01.01.0003.00001 |
250000000 |
| 8. |
APBD |
2026 |
Kab. Bone |
1.03.10.2.01.0055.5.2.04.01.001.00003.1.3.04.01.01.0003.00001 |
3020000000 |
| 9. |
APBD |
2026 |
Kab. Bone |
1.03.10.2.01.0055.5.2.04.01.001.00003.1.3.04.01.01.0003.00001 |
708141795 |
| 10. |
APBD |
2026 |
Kab. Bone |
1.03.10.2.01.0055.5.2.04.01.001.00003.1.3.04.01.01.0003.00001 |
1242573185 |
| 11. |
APBD |
2026 |
Kab. Bone |
1.03.10.2.01.0055.5.2.04.01.001.00003.1.3.04.01.01.0003.00001 |
1231151618 |
| Total Pagu |
22910906640 |
|
| Jenis Pengadaan |
| No. |
Jenis Pengadaan |
Pagu Jenis Pengadaan |
| 1. |
Pekerjaan Konstruksi |
21668333455 |
|
| Total Pagu |
22910906640 |
| Metode Pemilihan |
E-Purchasing |
| Pemanfaatan Barang/Jasa |
| Mulai |
Akhir |
| Agustus 2026 |
Agustus 2031 |
|
| Jadwal Pelaksanaan Kontrak |
| Mulai |
Akhir |
| Februari 2026 |
Agustus 2026 |
|
| Jadwal Pemilihan Penyedia |
| Mulai |
Akhir |
| Januari 2026 |
Februari 2026 |
|
| Tanggal Umumkan Paket |
30 Maret 2026 09:59 |